Case Studies
Planned Maintenance – removal and installation of equipment
The planned maintenance schedule of Tarmac Building Products (the largest producer of clay bricks and aircrete blocks in the UK) required a large heat exchanger for the condensate tank to be removed and replaced over the Christmas shutdown period. Lynx Engineers worked round the clock to remove the existing heat exchanger, using a 100 tonne crane and to install the replacement. Our team of slinger/banksmen, mechanical fitters and fabricators enabled the plant to start up on time following the Christmas break.
Breakdown Maintenance – plant repair work
LaFarge Cement UK, the UK’s largest cement maker, suffered a kiln breakdown. The kiln produced 520 tonnes per hour of cement, making it critical to get back on line as quickly as possible. Safety considerations included extreme heat and working at heights.
Whilst the kiln was cooling sufficiently for us to begin work we carried out a risk assessment and provided the customer with a method statement. As soon as it was safe to do so, our welders got to work on a half-hour-on, half-hour-off shift rota to minimise prolonged exposure to the heat and adverse working conditions. Within 48 hours the kiln was back on line.
Bridge Strengthening
Battersea Bridge was struck by a barge, causing significant damage and requiring the bridge to be closed to traffic. This caused major congestion in the Capital. Lynx Engineering were appointed by Costain Civil Engineering to re-strengthen the bridge (a project which required work to be done from marine vessels in the river directly underneath the bridge). The strengthening work and matching and replacement of the Victorian steelwork on the main facade enabled the bridge to be re-opened well ahead of the original schedule.
Fabrication and Installation – plant and equipment
ADM (Archer Daniels Midland Ltd) is one of the world’s largest agricultural processors of soybeans, corn, wheat and cocoa.
In order to speed up their ship-loading process ADM required the installation of three tubular steel Seed Outloading Booms.
Lynx won the competitive tender for their manufacture and installation. In order to be fitted during planned downtime, the booms were manufactured in advance in sections at our fully-equipped workshop. They were then transported by our crane lorry to the site. The booms were then assembled and ready to be installed by our team of skilled engineers during the planned shut. The project was delivered on budget and on time.
