Fabrication, Installation & Planned Maintenance - Factory production plant.
The planned maintenance schedule of Tarmac (the largest producer of clay bricks and aircrete blocks in the UK) required a large heat exchanger for the condensate tank to be removed and replaced over the Christmas shutdown period.
Lynx Engineers worked round the clock to remove the existing heat exchanger using a 100 tonne crane and to install the replacement. Our team of Slinger/Banksmen, Mechanical Fitters and Fabricators enabled the plant to start up on time following the Christmas break.